In shortA good STS crane breakdown investigation starts in the first hour: record what the crane was doing, save alarms and photos, and note what was repaired. Then classify the breakdown by system (hoist, trolley, boom, gantry, spreader, power or controls), check whether it is a repeat, and start a full root cause analysis when it meets your triggers.

The first-hour checklist

Classify by system

SystemQuestions to ask
Hoist and boom hoistMotor, brake, gearbox, wire rope or drive fault? Overload or slack rope?
Trolley and gantryDrive, motor, wheels, rails, limits or sensors?
SpreaderElectrical, hydraulic or mechanical? Twistlock or sensor faults?
Power and cable systemsFestoon, cable reel, switchgear, transformer or supply issue?
Controls and communicationPLC, network, sensors, software or settings change?

Is it a repeat?

Compare the failure with the crane's history and with the other cranes. Repeats on the same crane suggest a local cause, repeats across cranes suggest a common cause such as a specification, a procedure or the environment.

When to start a full root cause analysis

Set clear triggers so that the team does not argue each time. Common triggers are:

From checklist to RCA

The checklist gives you the facts. A root cause analysis then asks why until it reaches a cause you can control, and ends in owned actions. See how to do a root cause analysis in 5 steps.

Frequently asked questions

What is the difference between a breakdown report and an RCA?

A breakdown report records what failed and how it was repaired. An RCA goes further and finds why it failed, so the cause can be removed.

Which STS crane failures deserve a full RCA?

Repeat failures, long downtime, events with safety potential, and expensive damage. Set your own triggers and apply them consistently.

Run your own root cause analysis.
Describe the failure or add a photo or file, and RapidRCA builds the 5 Whys, fishbone, actions and report, using the ROOTS method.
Start an RCA

Last updated 14 October 2026. These guides explain a method and give examples. Always follow your equipment manufacturer's manual, your site procedures and applicable regulations.